Numerical Test Question 17 – Overtime cost calculation
Scenario
Three teams worked overtime. The overtime multiplier is applied to each team member’s normal hourly rate.
| Team | Overtime hours | Normal hourly rate | Overtime multiplier |
|---|---|---|---|
| Red | 96 | £18.50 | 1.5 |
| Blue | 110 | £17.00 | 1.25 |
| Green | 84 | £20.00 | 1.5 |
Question
What was the total overtime cost for all three teams?
- A. £7,281.50
- B. £7,671.50
- C. £7,421.50
- D. £7,521.50
Click to reveal the answer
Correct answer: D. £7,521.50
Members can unlock the full worked explanation for this question, including the calculation used to reach the answer and any important interpretation or rounding step.
Join our careers service to read more...
If everyone knew the best tricks and tips then they would no longer work! That is why the best guidance is for members only.
Subscribe to open the locked section on this page and get access to the full Civil Service Careers premium library.
Get help with applications, interviews, behaviours, personal statements, CVs, tests, workplace problems, promotions, and career decisions, all written for people who want a better result.
Already subscribed? Log in