Verbal Test Question 7 – River Flood Barrier Project

← Previous question  |  Back to question bank  |  Next question →

Read the passage and decide whether the statement is True, False or Cannot Say. Use only the information provided.

Passage

Construction of the East Mere flood barrier was scheduled to begin in April, but work was delayed when surveys identified protected nesting birds near the eastern access route. The project team changed the route rather than waiting until the nesting season ended. This required a revised traffic plan and additional ground testing, but allowed the main construction contract to begin in June. The barrier is still expected to become operational before the winter flood season, although landscaping work will continue afterwards.

Statement

The revised route added preparatory work while allowing construction to start before the nesting season ended and keeping the winter operational date achievable.

Answer options

  • True
  • False
  • Cannot Say
Click to reveal the answer

Correct answer: True

Members can unlock the full explanation for this question, including the wording or information gap that determines the answer.

Join our careers service to read more...

If everyone knew the best tricks and tips then they would no longer work! That is why the best guidance is for members only.

Subscribe to open the locked section on this page and get access to the full Civil Service Careers premium library.

Get help with applications, interviews, behaviours, personal statements, CVs, tests, workplace problems, promotions, and career decisions, all written for people who want a better result.

Already subscribed? Log in

Similar Posts